Oracle triggers 'force majeure' on $165bn Project Jupiter data centre after New Mexico pipeline is blocked
From the Newshound archive · first published 25 September 2026.

Oracle has invoked a force majeure clause against developer Blue Owl Capital over Project Jupiter — its data centre development in Doña Ana County, New Mexico — after regulators twice blocked a natural gas pipeline that the site depends on for power. The legal notice gives Oracle grounds to withhold payments to Blue Owl should the facility fail to reach operational status by 2028, though the company remains committed as the site's primary tenant. Oracle shares dropped roughly 5% on the news, sending ripples through AI financing markets more broadly.
New Mexico's State Land Office refused a right-of-way for a 17.8-mile gas pipeline, first in March and then again in July, citing emissions concerns and strain on local water supplies.